Compute
143.58K
H100-equivalent GPUs
IT power
103 MW
Current capacity
Capital cost
$3.9B
2025 USD · estimate

Site location
Loading site map
Site location
Google Midlothian
OpenStreetMap · Positron
OpenStreetMap · Positron styleOpen map
16 core fields4 timeline records4 chip records
Snapshot September 28, 2026
Source record
Facility fields
All fields supplied in Epoch AI’s data-center table. Values are kept as published.
- Name
- Google Midlothian
- Current H100 equivalents
- 143580.85118746842
- Current power (MW)
- 103
- Current total capital cost (2025 USD billions)
- 3.901846
- Owner
- Users
- Not reported
- Selected Sources
- - Site Map and Permit - City Council Presentation
- Calculations sheet
- https://docs.google.com/spreadsheets/d/13T5HLjkSCBKhOwSaOnxUcGqeSdfSF67ZSMVltEGywFM/edit?usp=sharing
- Project
- Not reported
- Current chip types
- TPU v7,TPU v6e
- All chip types
- TPU v7,TPU v6e
- Investors
- Not reported
- Construction companies
- Not reported
- Energy companies
- Not reported
- Country
- United States
- Address
- 3250 Railport Parkway, Midlothian, TX 76065