All datacentersFacility 02 / 93
Site record / Epoch AI

Microsoft Fairwater Atlanta

Microsoft · United States · 1435 Hwy 54 W, Fayetteville, GA 30214

Project Microsoft AI WAN

Compute

768.77K

H100-equivalent GPUs

IT power

636 MW

Current capacity

Capital cost

$24.09B

2025 USD · estimate

Satellite view of Microsoft Fairwater Atlanta
Satellite image · Epoch AIView image
Site location
Loading site map
Site location
Microsoft Fairwater Atlanta
OpenStreetMap · Positron
OpenStreetMap · Positron styleOpen map
16 core fields5 timeline records2 chip records
Snapshot September 28, 2026

Source record

Facility fields

All fields supplied in Epoch AI’s data-center table. Values are kept as published.

Name
Microsoft Fairwater Atlanta
Current H100 equivalents
768768.7220818596
Current power (MW)
636
Current total capital cost (2025 USD billions)
24.092952
Owner
Microsoft
Users
OpenAI #likely, Microsoft #likely
Project
Microsoft AI WAN
Current chip types
B200
All chip types
B200
Investors
Not reported
Construction companies
Not reported
Energy companies
Georgia Power
Country
United States
Address
1435 Hwy 54 W, Fayetteville, GA 30214
Source: Epoch AI, “AI data centers” · Retrieved September 29, 2026 · Licensed CC BY